How to Read a First Article Inspection Report for Cast Components

Published:2026-10-14    Category:Application Notes    Views:3
A first article inspection report is widely misunderstood as a document that proves one part was made correctly. It proves something more important: that the production process, as it will actually run, produces conforming parts. That distinction decides how the report should be read, and it explains why a report full of in-tolerance numbers can still be a reason to hold shipment.Casting first articles carry an extra layer that machined parts do not, because the properties of a casting cannot be measured on the casting itself. They are measured on material poured alongside it, which is a legitimate and standardised approach — but it has to be read with that in mind.

What a First Article Is For

A first article inspection is a complete, independent verification of the production process against the drawing and the specification. It is required when a new part enters production, and again whenever something changes that could affect the result: a design revision, a process change, new tooling, a change of manufacturing location or subcontractor, a change of material source, or a production gap long enough that the process cannot be assumed unchanged.

Two frameworks dominate:

  • AS9102 for aerospace, which defines a three-form structure and requires the first production article to be inspected against every drawing characteristic.
  • PPAP for automotive, which is broader and includes process capability, gauge studies and a part submission warrant alongside dimensional and material results.

Both share the same underlying purpose, and the review discipline is similar.

The Three AS9102 Forms

Form Title What it establishes
Form 1 Part number accountability That the report describes the right part at the right revision
Form 2 Product accountability That raw material and all special processes conform to specification
Form 3 Characteristic accountability That every drawing characteristic was measured and conforms

Form 1: Check the Identity Before Anything Else

Form 1 is short and is often skimmed, which is a mistake. If the part number, revision level or drawing issue does not match exactly what was ordered, nothing further in the report is valid, regardless of how good the numbers look.

  • Part number and description against the purchase order.
  • Drawing number and revision against the current released drawing. A report against a superseded revision is a common and serious finding.
  • Serial number or lot identification of the article inspected, and confirmation that it was taken from the production run rather than made specially.
  • Any additional customer or specification references called out on the drawing.

Form 2: Material and Special Processes

Form 2 is where the substance of a casting first article lives, because it covers everything that is verified by certificate rather than by measurement.

Item What to verify
Chemical composition All specified elements within limits, from the heat actually used
Mechanical properties Tensile, yield and elongation from test material poured with the casting
Hardness Measured on the casting or on a representative test piece, as specified
Heat treatment Cycle parameters, equipment and certification against the specified process
Non-destructive testing Method, standard, acceptance level and the operator’s qualification
Surface treatment Coating specification, thickness, adhesion and corrosion test results
Welding or repair Whether repair was permitted, by what procedure and with what verification

Casting-Specific Characteristics

This is the section that distinguishes a casting first article from a machined one. Several properties cannot be taken from the part itself and must come from material poured alongside it.

Characteristic How it is verified What to watch for
Tensile properties Separately cast test bars or coupons poured with the casting Confirm the coupon was poured from the same heat and given the same heat treatment
Chemical analysis Spectrochemical analysis of a sample from the pour Element limits are usually tighter for cast grades than for wrought equivalents
Internal soundness Radiography or ultrasonic testing to a specified severity level Acceptance level must match the drawing, not a default
Surface discontinuities Visual and penetrant testing, often after machining as well as before Some defects are only exposed when stock is removed
Microstructure Metallographic examination where the specification requires it Critical for duplex grades, where the phase balance governs properties
Dimensional tolerances CMM or gauge inspection against the declared casting tolerance grade Confirm the DCTG grade in the report matches the drawing callout
Mass and wall thickness Weighing, and ultrasonic or sectioned measurement where specified Wall thickness on cored features is subject to core shift

The test bar point is the one most often mishandled in review. A tensile result is only meaningful if the coupon came from the same heat, was cast under the same conditions and received the same heat treatment as the casting it represents. A certificate showing excellent properties from an unrelated coupon proves nothing about the deliverable.

Form 3: Reading the Ballooned Drawing

Form 3 is the dimensional heart of the report. Each drawing characteristic is numbered on a ballooned copy of the drawing and listed with its nominal, its tolerance, the measured value and a pass or fail result.

When reviewing Form 3, look for these things in order:

  1. Completeness. Every ballooned number on the drawing should appear in the report, and the count should match. Missing characteristics are the most common reason a first article is rejected.
  2. Nominal and tolerance accuracy. A transposed tolerance is worse than a failed dimension, because it can pass an out-of-specification part.
  3. Marginal results. A dimension sitting at the edge of its band is not a pass in a process-capability sense, even though it conforms.
  4. Which article was measured. The results should come from the first production article, not from a specially prepared sample.
  5. Datum consistency. Measurements should be taken from the drawing datum frame, not from whatever was convenient in the fixture.
  6. As-cast versus machined. Confirm that as-cast features are measured against casting tolerances and machined features against machining tolerances.

Common Findings and What They Mean

Finding Usual root cause
One characteristic out of tolerance Tooling dimension, shrinkage allowance or process variation
Several dimensions drifting in the same direction Systematic shrinkage error or pattern expansion factor
Wall thickness low on one side of a cored feature Core shift, not a dimensional error on the outside
Missing characteristics on the form Incomplete ballooning of the drawing
Material certificate does not match the heat used Documentation error or heat mix-up; a traceability failure
Radiography acceptance level not stated or wrong Acceptance criteria not taken from the drawing
Results identical to a previous report Report copied rather than re-measured; invalidates the submission
No evidence of the process used to make the article Sample made outside the production route

Partial and Full First Articles

When a change affects only some characteristics, a partial first article covering the affected items is normally acceptable. It is appropriate for a tooling wear correction, a change to one operation, or a change in a subcontracted process limited in scope.

A full re-submission is required when the change is broad enough that previously verified characteristics can no longer be assumed correct: a revision affecting multiple features, a change of manufacturing location, a change of material source, a significant process change, or a production gap after which the process cannot be treated as continuous.

The judgement call is whether the change could plausibly affect the characteristics not being re-measured. If the answer is not clearly no, a full submission is the safer route.

A Practical Review Sequence

  1. Confirm part number and revision on Form 1 match the order exactly.
  2. Confirm the article inspected came from the production run, with traceable lot or serial identification.
  3. Check Form 2 for material, heat treatment, NDT and coating, verifying that coupons and samples came from the same heat and process route.
  4. Confirm the declared casting tolerance grade matches the drawing, and that as-cast and machined characteristics are measured to the correct tolerances.
  5. Check that every ballooned characteristic appears on Form 3.
  6. Scan for marginal results, not just failures; a part at the edge of tolerance is a process warning.
  7. Verify that NDT acceptance levels, sampling and operator qualifications match the specification.
  8. Check that documentation is internally consistent: heat numbers, lot numbers, dates and quantities must agree throughout.
  9. Record any finding with its specific location and value, rather than as a general observation, so that the corrective action can be targeted.

Common Mistakes

  • Approving a report on the basis of the pass count, without checking that every characteristic was actually reported.
  • Accepting material properties from a coupon that was not poured from the same heat or heat-treated with the casting.
  • Failing to check that the drawing revision on the report matches the current released drawing.
  • Treating a first article as a one-off inspection rather than evidence about the production process.
  • Overlooking marginal results because they technically conform.
  • Not checking NDT acceptance levels against the drawing.
  • Accepting a report that does not identify which physical article was inspected.
  • Requesting a full re-submission when a partial one would suffice, adding cost and delay without adding confidence.

About ATM-Casting

ATM-Casting supplies first article inspection documentation for investment castings, structured to customer requirements including AS9102 and PPAP formats. Reports cover part and revision accountability, material and special process certification with heat-level traceability, and characteristic accountability against ballooned drawings, together with casting-specific evidence such as chemical composition, mechanical properties from test material poured with the casting, hardness, radiographic and penetrant testing, metallographic examination and dimensional inspection against the declared casting tolerance grade.

Chat

Chat Pre-sales Agent

Chat After-sales Agent

Chat

Request Callback

24h Callback Service

Enter your phone number and area code

Request Callback

WeChat Scan to Visit

WeChat QR Code

WeChat
Back to Top